MOUNT CARLTON GOLD SILVER & COPPER OPERATIONS
A 12 year life-of-mine (LoM) project based on a Reserve Estimate of 9.7million tonnes (Mt) containing 17,346,000ounces of silver, 34,000t of copper & 812,000ounces of gold. Open cut extraction at the V2 pit to be over 3 stages with 1.8Mt of stockpiled ore to be processing post completion. The 16 month operations for the A39 pit to commence 2 months after commencement of the V2 pit. Ore processing to include crushing, grinding & bulk sulphide flotation to produce a concentrate. Likely infrastructure to include a ROM pad, overburden dumps, sediment ponds, conveyors & stock piles, roads & tracks, power line, mine workshop, power station, process plant & associated buildings, topsoil dumps, accommodation camp, drainage diversions, tailings storage facility, decant pond, storm water pond & water storage reservoir.